# SMA 205: Grid incident - utility grid down / AC cable damaged / grid voltage too low

**Series:** SMA Sunny Tripower 3.0 / 4.0 / 5.0 / 6.0 (STPxx-3AV-40)

**Meaning:** Events 202, 203, 205 and 206 report that the utility grid has been disconnected, the AC cable is damaged, or the grid voltage at the connection point is too low, so the inverter has stopped feeding in. SMA directs the installer to check the miniature circuit breaker, the AC cable and the configured country standard, then to verify the grid voltage and involve the grid operator if the local grid is responsible.

## Likely causes
- Utility grid outage or miniature circuit breaker switched off
- Damaged or incorrectly connected AC cable
- Grid voltage below the permissible range at the connection point
- Wrong country standard configured

## Checks
- Ensure that the miniature circuit breaker is switched on
- Ensure that the AC cable is not damaged and is connected correctly
- Ensure that the country standard has been configured correctly
- Check whether the grid voltage is permanently within the permissible range; if not, contact the grid operator

## Parts implicated
AC wiring, AC circuit breaker

## Safety
Qualified installer only. High-voltage, grid-tied and battery systems can kill. Do not open energised DC/AC equipment. This page is a diagnostic reference, not step-by-step work instructions. Isolate and verify de-energised before any physical check, and escalate to a qualified installer/electrician for anything beyond reading the display or checking a connector on isolated equipment.

Safety flags: grid_tie

## Provenance
- [manual] p. 83 — "Explanation: The utility grid has been disconnected, the AC cable is damaged or the grid voltage at the connection point of the inverter is too low. The inverter has disconnected from the utility grid." — https://files.sma.de/downloads/STP3-6-3AV-40-BE-en-22.pdf (retrieved 2026-11-21)

- Confidence: verified
- Verified by: manual
- Requires qualified installer: yes