# SolarEdge 8x4F: Wrong AC connection

**Series:** SolarEdge single-phase and three-phase inverters (Europe & APAC)

**Meaning:** The inverter reports that its AC connection is wrong: one phase is landed on the wrong terminal. The addendum's remedy is to switch between L1 and L2, or between L2 and L3, connections.

## Likely causes
- L1 and L2 AC conductors swapped at the terminal block
- L2 and L3 AC conductors swapped at the terminal block

## Checks
- Isolate the AC supply and confirm the L1/L2/L3 landing against the installation guide
- Swap L1 with L2, or L2 with L3, as required and re-commission the inverter

## Parts implicated
AC terminal block, AC wiring

## Safety
Qualified installer only. High-voltage, grid-tied and battery systems can kill. Do not open energised DC/AC equipment. This page is a diagnostic reference, not step-by-step work instructions. Isolate and verify de-energised before any physical check, and escalate to a qualified installer/electrician for anything beyond reading the display or checking a connector on isolated equipment.

Safety flags: grid_tie

## Provenance
- [manual] p. 1 — "Wrong AC connection Switch between L1 and L2 or L2 and L3 connections" — https://web.archive.org/web/20230202122919/https://knowledge-center.solaredge.com/sites/kc/files/se-inverter-installation-guide-error-codes.pdf (retrieved 2026-11-21)

- Confidence: verified
- Verified by: manual
- Requires qualified installer: yes