Fronius IG / IG Plus (IG 15-60, IG 2000/3000/4000/5100) grid-tied inverters
Fronius 425: Communication with power stage set not possible
Quick answerFronius 425 means The operating interface cannot communicate with the power stage set; the inverter stops feeding..
Qualified installer only. This fault touches the AC grid connection, battery bank, DC bus, or an internal power stage. Isolate and verify de-energised, then escalate to a qualified installer/electrician.
What it means
The operating interface cannot communicate with the power stage set; the inverter stops feeding.
Likely causes
- Power stage set communication fault
What to check
- Contact a Fronius-trained technician if it persists
Parts implicated
None listed
Sources (verbatim):
- https://www.fronius.com/~/downloads/Solar%20Energy/Operating%20Instructions/42,0410,1089.pdf (manual, retrieved 2026-11-21) p. 89
“Communication with the power stage set is not possible”
Paraphrased; verify against the manual for your exact model and serial number.