Quick answerSMA 1001 means The L and N connections have been installed the wrong way round. SMA asks the installer to check the AC wiring between the inverter and the feed-in meter and to measure the AC voltages at the inverter connection, and to contact Service if the message persists..
Qualified installer only. This fault touches the AC grid connection, battery bank, DC bus, or an internal power stage. Isolate and verify de-energised, then escalate to a qualified installer/electrician.

What it means

The L and N connections have been installed the wrong way round. SMA asks the installer to check the AC wiring between the inverter and the feed-in meter and to measure the AC voltages at the inverter connection, and to contact Service if the message persists.

Likely causes

  • Line and neutral conductors swapped at the AC terminal
  • AC wiring fault between inverter and feed-in meter

What to check

  1. Check the AC wiring from the inverter to the feed-in meter
  2. Check the AC voltages on the inverter connection
  3. If the message is still displayed, contact SMA Service

Parts implicated

AC wiring