Quick answerSMA 9007 means The self-test that the inverter runs as part of the grid-connection configuration was terminated before it completed. SMA asks for the AC connection to be checked for correctness and for the self-test to be restarted..
Qualified installer only. This fault touches the AC grid connection, battery bank, DC bus, or an internal power stage. Isolate and verify de-energised, then escalate to a qualified installer/electrician.
What it means
The self-test that the inverter runs as part of the grid-connection configuration was terminated before it completed. SMA asks for the AC connection to be checked for correctness and for the self-test to be restarted.
Likely causes
- Self-test interrupted by the installer
- AC connection not correct, so the test could not complete
What to check
- Ensure that the AC connection is correct
- Restart the self-test
Parts implicated
AC wiring
Sources (verbatim):
- https://files.sma.de/downloads/STP3-6-3AV-40-BE-en-22.pdf (manual, retrieved 2026-11-21) p. 99
“Explanation: The self-test was terminated.”