SolarEdge single-phase and three-phase inverters (Europe & APAC)
SolarEdge 3x6D: Internal RGM error
Quick answerSolarEdge 3x6D means An internal revenue-grade meter (RGM) error was reported. The addendum says to check the energy meter CT wiring..
Qualified installer only. This fault touches the AC grid connection, battery bank, DC bus, or an internal power stage. Isolate and verify de-energised, then escalate to a qualified installer/electrician.
What it means
An internal revenue-grade meter (RGM) error was reported. The addendum says to check the energy meter CT wiring.
Likely causes
- CT (current transformer) wiring reversed, open or loose
- CT ratio or meter configuration mismatch
What to check
- Check the Energy Meter CT wiring against the meter installation guide
- Confirm CT orientation and that all phases are wired
- Re-commission the meter and clear the error
Parts implicated
energy meterCTs
Sources (verbatim):
- https://web.archive.org/web/20230202122919/https://knowledge-center.solaredge.com/sites/kc/files/se-inverter-installation-guide-error-codes.pdf (manual, retrieved 2026-11-21) p. 5
“Internal RGM Error Check, the Energy Meter CTs wiring.”
Paraphrased; verify against the manual for your exact model and serial number.