Qualified installer only. High-voltage, grid-tied and battery systems can kill. Do not open energised DC/AC equipment. Read the safety model.
SolarEdge single-phase and three-phase inverters (Europe & APAC)

SolarEdge 8xB8: Pairing error

confidence: verifiedchecked 2026-11-21
Quick answerSolarEdge 8xB8 means The inverter reports a Pairing Error, meaning it could not pair with its Power Optimizers during commissioning. The addendum's instruction is to contact support..
Qualified installer only. This fault touches the AC grid connection, battery bank, DC bus, or an internal power stage. Isolate and verify de-energised, then escalate to a qualified installer/electrician.

What it means

The inverter reports a Pairing Error, meaning it could not pair with its Power Optimizers during commissioning. The addendum's instruction is to contact support.

Likely causes

  • Power Optimizers not paired or paired to another inverter
  • Optimizer or string wiring fault during commissioning

What to check

  1. Note the code, serial number and optimizer serials
  2. Contact SolarEdge support before re-pairing

Parts implicated

power optimizers
Sources (verbatim):

Paraphrased; verify against the manual for your exact model and serial number.